Location Chatham, VA 
Owner: VDOT
Project Description:

Rt. 29 bridge replacement consists of redirecting North bound traffic to the South bound lane and replace the existing bridge by demolition down to the pier caps. The bridge will then be rebuilt and North bound traffic returned to normal.

Location Halifax, VA 
Owner: VDOT
Project Description:

This VDOT project consisted of 2 miles of roadway construction, roughly 200,000 yds of dirt moved as well as grading and storm drain installation under traffic control situations. Other activities conducted were stream relocation in jurisdictional areas, box culvert extension, and 57” bores underneath the roadway.

Location Columbia, VA
Owner: Henrico County


Project Description:

The Cobbs Creek Reservoir project is a 1500-acre site located off of the James River. Roughly 4 million yards of dirt has been moved. The project entailed the main dam roughly 3800 ft, two smaller dams, Control Tower, and Pump Station at the James River. The reservoir will be a 14.8-billion-gallon regional water supply impoundment located in Cumberland County, Virginia that will augment the flow of the James River as needed.  Water will be pumped out of the reservoir and into the James River in the drier months, and it will be pulled from the James River into the reservoir in the wetter months.  The reservoir will help during drought or near drought conditions by providing extra water to the flow of the James River

Location Lynchburg, VA   
Owner: Liberty University
Project Description:

Consisting of construction of a new dam on Opossum Creek to enlarge the existing Hydaway Lake for Liberty University and the relocation and construction of half a mile of roadway.

Location Ridgeway, VA   
Owner: Crown Cork Seal
Project Description:

Site prep of a 34 acre site for a manufacturing plant. Work included installation and maintenance of erosion control measures, 4,600LF of storm drain, installation of storm water filtration system, blasting and excavation of approximately 100,000 CY of rock, fine grade of building pad.

Location Christiansburg, VA   
Owner: VDOT
Project Description:

This project consisted of the demolition and reconstruction of the north and south bound bridges on I-81 at exit 114 over Route 8, the mainline of I-81 realigned, the exit 114 ramps adjusted adding two lanes to turn onto I-81 southbound off ramp Route 8 as well as a grade change at the approaches to the bridges

Location Baskerville, VA
Owner: Mecklenburg Co Public Schools
Size Approx. 120 Acres
Project Description:

Full Site preparation that included clearing, grading, moving approximately 800,000 CY of dirt, installing utilities and fine grading for building pads, roads, and athletic fields.

Location Boydton, VA
Owner: Confidential
Total Site Acreage: 110
Project Description:

Project work included over 1 million cubic yards of excavation on an accelerated schedule of only 6 months; 4,000 linear feet of storm drainage installation- including 72” Class 3 reinforced concrete pipe, 7,000 tons of Class 3 Rip Rap, 5,000 tons of Class 2 Rip Rap, over 3,000 tons of Class 1 Rip Rap......Click learn more for additional details. 

Location: Lynchburg, VA
Owner: City of Lynchburg
Total Size: Approx 1 Mile
Project Description:

Clear, Grade, and construction approx. 1 mile of new road way to VDOT specifications.

Location Ridgeway, VA   
Owner: Press Glass
Project Description:

Mass Excavation for Manufacturing Facility. Moved approximately 100,000CY of dirt in short time frame.